- Title
Settlement Analysis of Mud-Water Shield Passing Full-Face Water-Rich Sand and Cobble Stratum Under Luo River.
- Authors
Huang, Jianghua; Xu, Ping; Huang, Zhenlei
- Abstract
The shield construction of Line 2 of Luoyang Metro is designed to under-cross Luo River, the soils around the shield tunnels are composed of cobble, the permeability coefficient is about 140.0 m/d, the grain size of the cobble stratum is mainly from 2.0 to 10.0 cm, and the maximum grain size is up to 40.0 cm. Numerical simulations of the settlement caused by the shield construction under Luo River are carried out with finite element software of ABAQUS, and the calculated maximum cumulative ground settlement and settlement rate do not reach the monitoring alarm value. In order to ensure the safe construction of shield, control measures such as mud improvement, soil bin pressure, synchronous grouting pressure and secondary grouting during the shield structure construction are proposed. The in-situ measured results of the settlements during the shield tunneling process show that the maximum accumulated settlement and settlement rate don't reach the monitoring alarm value, and the left and right shields crossed Luo River safely, which is consistent with the numerical simulation results. The shield tunneling measures and research methods proposed in this paper can provide references for similar projects in future.
- Subjects
GROUTING; SAND; GRAIN size; TUNNELS; TUNNEL design &; construction; TUNNEL ventilation
- Publication
Geotechnical & Geological Engineering, 2024, Vol 42, Issue 1, p535
- ISSN
0960-3182
- Publication type
Article
- DOI
10.1007/s10706-023-02587-2